Pleasant Valley Neighborhood Park #1

  • The City will construct a neighborhood park to include open space, active use areas, scenic lookout, playground and trees and shrubs. Wayfinding signs will help park visitors navigate between the park and Kelley Creek Trail.

    Construction is expected to begin mid-August and should be complete by winter 2019.

    Park amenities

    • Playground
    • Benches
    • Half-court basketball
    • Picnic shelters
    • Path
    • Pleasant Valley Neighborhood Park site plan for gallery
    • Pleasant Valley Neighborhood Park #1
    • Pleasant Valley Neighborhood Park #1 - photo 2
    • Pleasant Valley Neighborhood Park #1 - photo 3
    • Pleasant Valley Neighborhood Park #1 - photo 5

    1 of 5
    • View larger version of the site plan.

    • Site of the future Pleasant Valley Neighborhood Park #1

    • Site of the future Pleasant Valley Neighborhood Park #1

    • Site of the future Pleasant Valley Neighborhood Park #1

    • Site of the future Pleasant Valley Neighborhood Park #1

  • Construction

    Schedule

    • Mid-August to Spring 2020
    • Monday - Friday, with some weekend work possible
    • 7:00 am - 5:30 pm 

    Impacts

    • Traffic delays possible
    • Construction equipment may be parked in streets
    • Construction noise and dust
    • Please avoid the park area; some fencing may be put up
    • Regional trail will be open during construction

    Contact

    Report speeding construction trucks to the Gresham non-emergency line at 503-823-3333.

    For all other park construction-related questions, contact Mike Green at Michael.Green@GreshamOregon.gov.