Commercial Building Permit Process/Timeline

Action Time
Plan Review and First Comments - New Construction/Additions 21 days
Plan Review and First Comments - Tenant Improvements and Remodels 14 days
Plan Review and First Comments - Signs, Renewable Energy, Miscellaneous 7 days
Re-Reviews 7 days

 

Actual time may vary based on requirements such as traffic studies, fire-supply or fire-access issues, etc.

If you have specific questions about the timing for your project, please contact us.

 

 